Mumbai’s airport operator has asked airlines to submit transition plans by November 3 after a roughly 90-minute meeting on Wednesday ended without agreement on moving foreign-carrier services to Navi Mumbai. Airlines sought more information before committing, while Mumbai International Airport Ltd held to its target of relocating traffic equivalent to five million annual passengers by the end of March 2027.
The proposed move would create room for redevelopment at the existing airport. Indian carriers have already announced phased transfers accounting for about three million annual passengers, leaving the operator seeking further commitments from foreign airlines to reach its target. The figures describe annual traffic, not five million passengers who would all move during the transition period.
Air France-KLM regards splitting its operations between Mumbai’s Terminal 2 and Navi Mumbai as 'operationally inefficient'. Reportedly Emirates has argued that Navi Mumbai lacks the operational capacity to accommodate large-scale operations by global airlines.
Moving a departure means moving more than the aircraft. Its passengers, baggage, handling teams, crew arrangements and connecting services must be ready at the same airport. Dividing flights between two sites can leave a carrier supporting two operations while carrying the same overall traffic.
The difficulty is particularly acute for connections. A passenger arriving on a domestic partner flight needs to reach the international departure with enough time for baggage transfer, check-in where required, security and immigration. If the flights use different airports, surface travel becomes part of that itinerary rather than simply the journey from home.
The published accounts of Wednesday’s meeting do not include a carrier-by-carrier plan covering those connections, partner schedules, ground handling, lounges, cargo, crew positioning or travel between the airports. Airlines sought further details before agreeing to relocate.
Some carriers asked for time until the next winter schedule, beginning in October 2027. Airlines also pressed for Terminal 1 redevelopment to proceed in phases and opposed a unilateral reduction in slots from the summer schedule starting in March 2027, according to people familiar with the discussions.
MIAL presented redevelopment schedules and assured airlines that the five-million-passenger volume of temporarily transferred international traffic would be restored to Mumbai after Terminal 2 expansion. That assurance concerns the eventual return of traffic, it does not establish the individual flight numbers or dates involved in either direction.
The November 3 deadline is therefore for plans. It comes alongside several other dates in the negotiations, the original October 25 transition proposal, the deferred summer-2027 programme, MIAL’s end-March target and the October 2027 timing sought by some airlines.
Air India, Air India Express, IndiGo and Akasa have announced phased moves jointly with Adani Airport Holdings. Their commitments give Navi Mumbai an initial international network, but do not settle the arrangements for foreign airlines or their passengers.
Wednesday’s meeting left those commitments unresolved. The next formal milestone is November 3, when MIAL wants airlines’ transition proposals. Until individual schedules are confirmed, passengers should not read the operator’s traffic target, or the deadline for submitting a plan, as notice that their flight has changed airports.